Restoration Project of 2023/2024
In Pursuit of Better Acoustics to Worship the Lord
Beginning of Ceiling Restoration Project (Pews are Moved Out) --CLICK FOR VIDEO
The Sanctuary Restoration Project was completed in February of 2024.
12/04/23
Original floor reveals that there used to be an old room here, used as a quiet place for mothers and children (notice wall and door opening).
12/04/23
Original floor is uncovered--revealing well-worn pocked surface, but what a beautiful color!
11/21/23
"Glory to God in the Highest" put up, tan glazing done and gold paint started around medallion center vent.
11/10/23
Ceiling after primer, painting and repairs.
10/26/23
09/10/23
We’ve been worshiping in the Fellowship Hall since 8/13/23.
08/22/23 - 09/08/23
Ice blasting old paint off ceiling is done.
09/10/23
Joel Skinner (Church Interiors) reported that ceiling repairs will be done the next couple of weeks, then painting will begin.